The compute build-out.
Why it sets the pace.

AI training compute has grown about fivefold a year since 2020, and the buildings, chips and power stations are catching up. Here is the evidence, and what it means for what you pay.

28 November 2026 · 8 min read · By the HOPE team

The three inputs

Modern AI models are produced by three things: data, algorithms and compute. Compute is the one you can count, buy and plug in, which makes it the easiest to track and the one with the loudest numbers attached. This article follows it from the training run, to the chips, to the building, to the power station, and then to your bill.

Two cautions first. Compute is an input, not a guarantee: more of it has so far produced better models, but nothing in the numbers below says it must continue to. Also, many of the money figures here come from company guidance and press coverage, so they change quarterly. We say "as of" and give the month throughout.

Training compute: about five times more each year

Epoch AI keeps the most-used public dataset of how much computation went into training notable models. Its current trend page (updated 5 November 2026) puts the growth of frontier language-model training compute at about 5x per year since 2020, a doubling time of about 5.2 months, with a 90% interval of 4.6 to 6.0 months.

This is not a new finding. In a May 2024 analysis, Epoch found compute growing at 4 to 5x per year across notable models since 2010 (about 4.1x) and for frontier models after the slowdown around 2018 (about 4.2x), with frontier language models at about 5.0x since mid-2020. It also tested the trend backwards: a 4x-a-year extrapolation from GPT-3 (3e23 FLOP, May 2020) predicted about 4e25 FLOP by December 2023, and the two models that arrived near then, GPT-4 (about 2e25) and Gemini Ultra (about 5e25), landed close to that line.

Compounding is hard to feel, so here is plain arithmetic of our own: five times a year for six years multiplies the compute by roughly 15,000. That is the gap between the models of 2020 and the ones you use today, in raw training computation. Epoch's authors are careful about their uncertainty. The intervals are wide for several of their estimates, and they note that the trend could have accelerated.

From chips to buildings

Compute has to live somewhere. The unit that matters for the largest runs is no longer a server rack; it is a campus drawing as much power as a small city. Epoch tracks the biggest AI data centres by IT power capacity. In a September 2026 analysis it found that since mid-2024 the record for the largest single AI data centre has doubled about every ten months.

Aug 2024 · Google Papillion237 MWFeb 2025 · Colossus 1278 MWJun 2025 · New Carlisle398 MWDec 2025 · New Carlisle626 MWMar 2026 · New Carlisle910 MWJun 2026 · Colossus 2946 MW
Largest AI data centre by estimated IT power at each date a new record was set. Source: Epoch AI, 4 September 2026. Epoch says about 80% of the time an estimate lands within a factor of 1.4 of the true value.

Epoch's live chart, updated 27 November 2026, now lists the five largest as Colossus 2 at 1,246 MW, Anthropic-Amazon New Carlisle at 1,037 MW, OpenAI's Stargate Abilene at 824 MW, Microsoft Fairwater Atlanta at 636 MW and DayOne Nusajaya at 473 MW. Epoch's trend page estimates Colossus 2 at about 1.5 million H100-equivalents of computing capacity. For scale: the 237 MW record of August 2024 has been overtaken about five times in under two and a half years.

The same September analysis lists planned sites that would take the record higher, to about 1.5 GW in 2027 (Colossus 2) and about 2.3 GW (Microsoft Fairwater Wisconsin, projected for May 2028). Those are projections. Buildings slip, power connections arrive late, and plans change.

The money

Chips and buildings cost money, and the large cloud companies are paying it. The picture below mixes dates because the companies report on different days; check each before relying on it.

Company2026 capital spendingAs of
MicrosoftAbout $190bn (calendar 2026), including $25bn tied to higher component pricesApril 2026
Alphabet$195bn to $205bn; Q3 spend $51.4bn, up 114% on a year earlierOctober 2026
AmazonApproaching $200bn (January guidance, said to be "largely the same")April 2026
Meta$125bn to $145bnApril 2026

In April 2026 Yahoo Finance summed the top ends of the ranges at about $725bn for the year. Alphabet's October results, as reported by XTB, showed third-quarter capital spending of $51.4bn and a full-year range of $195bn to $205bn. We could not open the October releases from the other three companies in this research, so their rows are older. Treat the $725bn as an April figure, not a current total.

The chip maker sees it directly. On 17 November 2026 Nvidia reported third-quarter revenue of $115.8bn, up 103% on the year, of which Data Center was $107.6bn, up 110%. It guided the next quarter to $130bn, plus or minus 3%.

Power

A gigawatt campus is a grid problem. The International Energy Agency's Energy and AI report (2025) puts global data-centre electricity use in 2024 at about 415 TWh, roughly 1.5% of world electricity, after growing about 12% a year over the previous five years. Its base case roughly doubles that to about 945 TWh by 2030, just under 3% of global electricity. Servers built for AI grow about 30% a year in that case and account for almost half of the net increase. The United States adds about 240 TWh, up 130% on 2024, and the US and China together make up nearly 80% of the growth to 2030.

Those numbers are a projection from 2025, made before several of the 2026 announcements above. They are useful for scale, not as a forecast to quote to the decimal. The point that survives is simple: the build-out is limited by electricity, land and equipment lead times as much as by money. That plausibly shapes how fast the record for one site can grow, though none of the sources above isolates the cause.

Will the curve bend?

Extrapolation is easy and often wrong, so it helps to put two of Epoch's own numbers side by side. Its log-linear fit to the record-holders, which started at about 207 MW in August 2024, reaches about 5,500 MW by late July 2028 if the doubling every ten months continues. The sites Epoch can actually name as planned top out lower: about 1,676 MW for Meta Hyperion in January 2028, and about 2,263 MW for Microsoft Fairwater Wisconsin in May 2028. The gap between a trend line (about 5.5 GW) and the announced pipeline (about 2.3 GW) is where the uncertainty sits. Either new sites are announced that nobody has listed yet, or the trend slows.

The financial side has the same shape. Capital spending guidance for 2026 is in the hundreds of billions, and Alphabet's full-year range implies about $63bn to $73bn in the fourth quarter alone, against $51.4bn in the third (XTB's arithmetic). Whether that is repaid depends on demand for the products built on top, which is a question for the adoption evidence in the next article in this series. Surveys there show use spreading widely while agent use is still thin. We do not know how those two will meet.

What would change the picture: a power connection that arrives two years late, a run of models that scale compute without scaling skill, a sharp fall in the price of chips or memory, or a method that gets today's capability from far less compute. Epoch's price work shows the last of these has already happened for a fixed level of performance. It shows nothing about the highest level.

What it means for capability and price

Capability. More compute lets labs train larger models for longer and also run more reasoning at the moment you ask a question. Both show up in what an agent can finish. We cannot give you a clean law that links a number of FLOP to a skill, and we did not find one in Epoch's work. What the data supports is narrower: the inputs have grown about fivefold a year for six years, and the benchmark results in When benchmarks run out and the task lengths in The length of tasks AI can finish keeps doubling have risen over the same period. That is correlation across a period, and not a proof.

Price. Here the news is mixed. Epoch found in March 2025 that the price of reaching a fixed level of performance fell fast: about 40x per year to match GPT-4 on a PhD-level science test, and between 9x and 900x per year depending on the benchmark. It warned that the fastest drops were recent and might not last. The cheaper tokens did not shrink the total spend. The capital figures above are rising, and Microsoft attributes $25bn of its 2026 plan to higher memory and component prices. Cost per unit of capability has fallen; the total spend on the whole build-out has not. The article on the falling price of intelligence goes deeper on the first half.

Supply. Compute is also a constraint on how much can be served. We found no source that quantifies shortages, so take this as a reasonable expectation, not a measured fact: a company building on agents should expect usage limits and changing terms, and plan for them.

What this means for operators

You do not need to buy a GPU to be affected by any of this. You will meet the build-out as a stream of new models, new prices and new limits. Operating well under that stream looks like this.

  1. Assume the model under you will change. Build your setup (rules, skills, hooks, tests) so that it carries to the next model. This is what the compounding module teaches: every correction becomes a rule that outlives a particular model.
  2. Budget by task, not by token. Tokens get cheaper while agents spend more of them per task. Track what a finished, verified task costs you, in money and in minutes. The economics module covers models, effort levels and when to stop.
  3. Match the model to the work. A cheap, fast model for routine edits and a stronger one for planning and review is usually a better spend than the biggest model everywhere. Test it on your own tasks, as discussed in the benchmarks article.
  4. Plan for limits. Keep work in sessions that can pause and resume, keep a second harness or model configured, and keep important context in files, not in a single long chat. See decomposition.
  5. Keep a human on the gate. More compute lets agents run longer and touch more. That raises the value of permissions and checks. Guardrails is the module for it.

For the bigger frame, read what operating a harness means.

Sources

All pages were opened for this article between 27 and 28 November 2026. Figures marked "as of" move; check the source for the current value.

  1. Trends in training compute, Epoch AI, updated 5 November 2026.
  2. Training compute of frontier AI models grows by 4-5x per year, Epoch AI (Sevilla and Roldán), 28 May 2024.
  3. The record for power capacity in a single data center has doubled every 10 months, Epoch AI, 4 September 2026.
  4. Largest AI data centers by power capacity, Epoch AI, updated 27 November 2026.
  5. Energy and AI: Energy demand from AI, International Energy Agency, 2025.
  6. Magnificent 7 earnings rush reveals AI spending surge, Yahoo Finance (Myles Udland), 30 April 2026.
  7. Alphabet disappoints Wall Street despite record results, XTB, 29 October 2026.
  8. NVIDIA Announces Financial Results for Third Quarter Fiscal 2027, NVIDIA, 17 November 2026.
  9. LLM inference prices have fallen rapidly but unequally across tasks, Epoch AI, 12 March 2025.